How to choose a UPS for a server room

When power goes off every day, the UPS in a server room works at its limit. How to calculate the load, choose the UPS type and batteries, remember the air conditioner and set up graceful shutdown.

DIXI-CENTER · Published · Verified

When outages follow a schedule, the UPS in a server room discharges and recharges almost every day. Its job is to keep the servers from rebooting during a short outage or voltage dip, and in a long outage to hold on until the generator starts – or give the systems time to shut down cleanly.

Load list and power headroom

First list everything that has to run on the UPS. Besides servers and storage, that means switches (including those on other floors), the router and firewall, the provider’s optical terminal, the KVM console (a monitor and keyboard in the rack), server room sensors and cameras. The network is easy to miss in such a list, and without it nobody can reach the server.

You need the actual consumption of each device. The server’s remote management controller (iLO, iDRAC and the like) or a metered power distribution unit in the rack (PDU) will show it. The figure on a power supply is its maximum; a running server usually draws less.

UPS capacity is stated twice: in watts and in volt-amperes (VA). Watts are the real power the equipment draws, VA is apparent power, and the ratio of watts to VA is the power factor. The load must not exceed either of the two UPS ratings (Schneider Electric (opens in a new tab)). By industry convention a UPS’s watt rating is about 60% of its VA rating, but in newer UPSs the two values are closer, and some online UPSs have a unity power factor (Schneider Electric (opens in a new tab), Schneider Electric blog (opens in a new tab)).

Server power supplies in a high efficiency class (labeled 80 PLUS Platinum) have a power factor of at least 0.95 at half load (Wikipedia (opens in a new tab)), so their VA is almost equal to their watts. A UPS’s watt rating is never higher than its VA rating, so with servers the watt rating runs out first. That makes watts the deciding figure for a server room. Check your list against both values on the datasheet of the specific model.

Now the headroom. Take a UPS with a VA rating 1.2 times the total load in VA (Eaton (opens in a new tab)). Another recommendation is to keep the load at around 80% of maximum capacity, because near the limit efficiency drops, heat rises and runtime shrinks (Schneider Electric (opens in a new tab)). An example: two servers at 350 W, storage at 250 W and network equipment at 150 W add up to 1100 W. With a 1.2 margin that’s about 1300 VA (for servers, VA is almost equal to watts, so take 1100 VA and multiply by 1.2), and with the 80% rule about 1400 W (1100 ÷ 0.8). So pick a UPS rated at least 1400 W: its VA rating is no lower than its watts, so it also meets the 1300 VA condition. If new servers are coming to the rack soon, include them now.

Line-interactive or online

In a line-interactive UPS, utility power passes through a regulator that boosts low voltage and trims high voltage. When the voltage is lost, the UPS switches to battery. These units suit server racks and office networks.

An online double-conversion UPS works differently. It rectifies incoming AC into DC, and an inverter turns it back into clean AC, free of fluctuations and distortion. The transfer to battery has no interruption at all. These UPSs are used for mission-critical equipment in server rooms and data centers (Eaton (opens in a new tab)).

A cabinet with network equipment and one or two non-critical servers often gets by with a line-interactive UPS, but one with a pure sine wave output (smooth voltage, without “steps”): some power supplies may see stepped voltage as a power failure and shut down (CyberPower (opens in a new tab)). If servers and storage must not reboot and power comes from a generator or an unstable grid, choose online. The frequency range of small generators can be wider than a line-interactive UPS accepts, and then such a UPS switches to battery for no reason, while an online UPS accepts wide variations in voltage and frequency (UPS Systems (opens in a new tab)). Look for generator or hybrid inverter requirements (more on that below) in the UPS documentation.

Runtime and batteries

The internal batteries of most UPSs last 10 to 15 minutes (Eaton (opens in a new tab)). That’s enough to wait for a generator or shut systems down cleanly, but not to sit out an outage of several hours. Runtime also depends heavily on load. In a Schneider Electric example, one and the same UPS runs about 9.5 minutes at 80% load and only 6.5 minutes at full load. The manufacturer warns that this is just an example and advises checking the runtime graph of the specific model (Schneider Electric (opens in a new tab)).

External battery modules help it hold on longer. Depending on the load and the number of modules, runtime can reach several hours (Eaton (opens in a new tab)). The more modules, the longer the built-in charger takes to restore charge. If power is back for only a few hours between outages, batteries may not fully recharge and runtime shrinks day by day. So check the datasheet for the charge time with the number of modules you need.

With frequent outages, battery type matters a lot. Battery life is counted in discharge cycles, and UPSs aren’t designed for regular deep discharges (APC, a Schneider Electric brand (opens in a new tab)). Lead-acid batteries were the standard for a long time. Lithium-ion batteries, according to Eaton, last longer, take up less space and recharge faster (Eaton (opens in a new tab)). Every battery is designed for a limited number of cycles, and the deeper the discharge, the fewer it survives (Riello UPS (opens in a new tab)). With scheduled outages, lead-acid batteries discharge almost daily and may last noticeably less than the usual 3–5 years, so watch their condition and budget for replacement earlier. Fit only the lithium batteries the manufacturer approves for the specific UPS model. Swapping lead-acid for lithium yourself is dangerous and can void the warranty.

Phases, redundancy and power distribution

Offices and other small consumers usually have single-phase power, larger sites three-phase, and then a three-phase UPS is needed (Eaton (opens in a new tab)). A single cabinet usually gets by with single-phase; for several racks of servers and storage, three-phase is worth a look. What line comes into the room and what load it can carry, battery charging included, is for your electrician or design contractor to say. DIXI-CENTER doesn’t lay power lines or do electrical work; we rely on the answer from your electrician or design firm.

N+1 redundancy means one more UPS module than the load needs. For example, in Eaton’s setup three paralleled UPSs are installed: two feed the load, the third is in reserve. If one fails, it is disconnected and the load stays protected (Eaton (opens in a new tab)). A smaller server room keeps it simpler: two UPSs on two independent A and B feeds, with dual-supply servers connected to both.

PDUs distribute power around the rack. Basic ones just distribute it. Metered input PDUs show the load of the whole rack, metered outlet PDUs show the consumption of individual devices. Managed PDUs let you switch outlets on and off remotely (Eaton (opens in a new tab)). A device with a single power supply is connected to both feeds, A and B, through a rack transfer switch (ATS): it moves the device to the other feed on its own if one fails.

When a UPS isn’t enough: generators and hybrid inverters

If the power is out for hours, the UPS works together with a generator. The UPS’s job then is to hold for one to five minutes (Eaton (opens in a new tab)) while the generator starts and the automatic transfer switch moves the line over. The transfer switch and generator connection are electrical installation work done by specialist contractors.

A hybrid inverter combines the grid, solar panels and a battery bank. Batteries are chosen to match the voltage of the specific inverter: Deye low-voltage hybrid inverters, for example, are almost all designed for 48 V, one model for 24 V (Deye (opens in a new tab)). The transfer time to battery is on the inverter’s datasheet and is worth comparing with the zero transfer time of an online UPS: servers shouldn’t see even a short interruption. In a server room the inverter is usually placed in the power line upstream of the UPS rather than replacing it: the UPS covers the switchover gap. Large battery systems are subject to separate room and fire safety requirements.

Cooling during an outage

The UPS keeps the servers running, but the air conditioner usually isn’t on it. A closed server room without cooling gets hot very quickly, and equipment may shut down from overheating before the batteries run out. So the air conditioner is connected to a generator or inverter (allowing for the compressor’s inrush current), and a temperature probe goes into the UPS network card (more on it below), so that systems can shut down on temperature as well as battery charge (Schneider Electric (opens in a new tab)).

Shutdown, testing and maintenance

When the battery is running down and power doesn’t come back, the servers should shut down on their own. For this, the UPS is connected to the local network through a network card and the manufacturer’s shutdown software is set up. APC’s PowerChute Network Shutdown shuts down virtual machines in the correct sequence, and each Smart-UPS series UPS needs its own network card for this software (Schneider Electric (opens in a new tab)). Eaton’s Intelligent Power Protector gets UPS data over USB or a network card and shuts down computers and virtual machines when an outage drags on (Eaton (opens in a new tab)).

Agree with your administrators in advance at what charge to start shutting down and in what order. Think about powering back on too. Storage has to start before the servers, and the UPS should restore output only once the battery has recharged to a set minimum. Otherwise, with several outages in a row, servers start up and immediately shut down again.

After installation, always switch the UPS to battery under the real load. Check the transfer, the actual runtime, notifications and the shutdown scenario – and only then put the equipment into service.

Then comes regular maintenance. APC advises running a runtime calibration test (a separate test that refines how long the UPS will last on battery) once or twice a year and only when necessary, because frequent tests noticeably shorten battery life. Most APC batteries last three to five years. The best temperature for lead-acid batteries is 20–25 °C, and every 8 °C above that halves their life. It’s warmer inside a UPS than in the room, so ventilation and cooling are needed. The manufacturer advises replacing sealed lead-acid batteries before they reach five years of age and storing new spare batteries for no more than six months after purchase, since they gradually discharge in storage and leave the factory at about 80% charge (APC (opens in a new tab)). Put battery replacement in the plan right away.

If you need it, DIXI-CENTER can size the UPS, supply it and set up graceful server shutdown; the scope of work is on the UPS & Power page and in the Power and Continuity solution. For servers running AI, see also AI workstation or GPU server.

What to include in your email

  • a list of equipment that has to run on the UPS, with actual consumption or server models
  • the required runtime and what should happen after it: switchover to a generator or shutdown
  • whether the server room has a single-phase or three-phase supply and what capacity the line allows
  • whether there is a generator, an automatic transfer switch or solar panels
  • whether the server room air conditioner is powered during an outage
  • the number of racks, free space in them, temperature and ventilation in the room
  • which UPSs are already installed and how old their batteries are
  • which systems to shut down and in what order

These points are already in the email – just add your answers.